Full panel and a 65-foot run through a finished basement
The garage was two rooms away from the panel. Most electricians quoted three visits. We did it in one.
Edina, MN
2024 Ford F-150 Lightning (Extended Range)
The Situation
The homeowner had owned a 2024 F-150 Lightning for six weeks and was still charging from a 120 V outlet in the garage — adding roughly 5 miles of range per hour. The garage is a three-stall detached unit attached to a 1978 colonial. The electrical panel is a 100-amp Federal Pacific Stab-Lok in the basement utility room, separated from the garage by a finished family room, two walls, and a utility chase. Three general electricians quoted the job. Two said the panel needed replacing before any charger work. The third said he could run conduit exposed along the finished ceiling — something the homeowner refused.
What We Found On-Site
- Federal Pacific Stab-Lok panel: 100 A service, 26 of 30 slots occupied, no capacity for a 50 A double-pole breaker without load shedding or a panel replacement.
- Finished drywall ceiling between panel room and garage — no accessible chase.
- Existing 240 V dryer circuit (30 A) adjacent to the garage — routed through the same chase needed for the EV run.
- No grounding electrode system bonded to the water main (code deficiency unrelated to EV work, but required to correct before permit sign-off).
- Garage sub-panel stub-out already roughed in from a 1994 renovation — unused 60 A feeder wire, never energized.
What We Did
- 1
Load calculation & panel assessment
Ran a full NEC Article 220 load calculation. The existing 100 A service had adequate headroom on calculated demand — the panel's problem was physical slot count, not service size. Identified the unused 1994 feeder wire: 6/3 AL SEU cable rated for 60 A, routed inside the wall cavity from the panel to the garage ceiling.
- 2
Tandem breaker substitution + feeder activation
Replaced two standard single-pole 15 A breakers with UL-listed tandem breakers, freeing two slots. Installed a 60 A double-pole breaker feeding the 1994 AL feeder. Terminated the feeder at a new 60 A sub-panel in the garage — two-slot, flush-mount, in the corner behind the door.
- 3
Grounding electrode system correction
Installed a 4 AWG ground wire from the panel neutral/ground bar to the copper water main entry, bonding per NEC 250.52. Drove an 8-foot ground rod at the exterior foundation as supplemental electrode.
- 4
Circuit pull inside the garage
From the new 60 A sub-panel, pulled 6/2 NM-B (copper) through the garage attic space to the charging location on the left wall — 18 feet of clean concealed wire. Installed a 50 A double-pole breaker in the sub-panel.
- 5
Charger mounting and commissioning
Mounted ChargePoint Home Flex on a flush steel plate at 48 inches AFF (standard for garage EV charger). Connected to the homeowner's Wi-Fi network, configured charge scheduling to align with Xcel Energy off-peak rates (9 PM – 9 AM), and tested at full 50 A output for 20 minutes confirming 11.5 kW draw.
- 6
Permit and inspection
Pulled Edina electrical permit before work. City inspector visited on day 3. Passed first inspection — no corrections required. Certificate of compliance mailed to homeowner.
Outcome
The F-150 Lightning now adds approximately 30 miles of range per hour of charging (vs. 5 on 120 V). A full charge from 20% to 100% takes under 7 hours overnight. The homeowner enrolled in Xcel's EV-TOU rate and estimates saving $28–$34/month on electricity vs. daytime charging rates. Total project cost: $2,340 including permit.
Before & After
Installation Specs
- Circuit
- 50 A / 240 V dedicated
- Wire run
- 6/2 NM-B copper, 18 ft concealed
- Sub-panel added
- 60 A, 2-slot, flush-mount garage
- Output
- 11.5 kW / ~30 mi range per hour
- Permit
- Edina electrical — passed first inspection
- Project duration
- 1 day on-site + 1 inspection visit
Charger Installed
ChargePoint Home Flex — 50 A dedicated circuit, NEMA 14-50
“Three other electricians wanted to gut the panel or leave conduit strapped to my ceiling. These guys found wire I didn't know I had and ran a clean install in one day.”